Packaging SC Campina da Alegria

Expansion

The expansion of the manufacturing unit includes the following objectives:

  • Process automation and optimization
  • Expansion of competitiveness and operational excellence
  • Increase of Production capacity

Impacts

Production capacity

increase of the production of packaging wavy carton at SC unit
0 %

Products

Gaia II investments take place at the Packing Plant of Campina da Alegria, in Vargem Bonita (SC), considering the following products:

Wavy carton sheets

Type bag wavy carton boxes

Type cut and fold wavy carton boxes

Investment

The Gaia II project has the following indicators:

Estimated investment

R$ 150.433 k

Planned work execution term

34 months

Investment made (until 03/31/26)

R$ 131.249 k

Modernização

Nosso robusto plano de expansão trará resultados consistentes em nossa Unidade Embalagem SC: modernização de equipamentos, automatização de processos e aumento de capacidade produtiva.

Galeria de Imagens

Marcos de entrega

Andamento 

100%

Acompanhe o andamento macro das etapas do projeto e suas datas de entrega previstas.

2020Marcos de Entrega1º tri1º tri1º tri2º tri2º tri2º tri3º tri3º tri3º tri3º tri4º tri4º tri4º tri4º tri202120222023Detalhamentoe EngenhariasAmpliação daExpediçãoBarracão de paletesNova OnduladeiraNova Impressora FFGLinha de acabamentoDescontinuidadeOnduladeira 2Impressora WardStartup (Plan)Startup (Tendência)Prazo (Plan)Prazo (Tendência)