Paper SC Campina da Alegria

Modernization

  • Frequency conversion from 50hz to 60hz
  • New transmission line
  • New generators and turbines
  • Infrastructure improvements
  • New power house

Gaia V – São Luiz Repowering was approved with a projected Capex of BRL125.9 million. The project aims to expand capacity, improve efficiency and promote the sustainability of renewable energy supply at the Vargem Bonita (SC) units, contributing to the Company’s ESG Cycle 2030 Commitment to self-sufficiency in renewable energy generation.

Investment

The ongoing expansion, for the Gaia V project, has the following expectations:

Estimated investment

R$ 125,881 K

Planned work execution term

30 months

Investment made (until 30/06/26)

R$ 20.447 k

Image Gallery

Delivery milestones

Andamento

25%

Follow up the project stage macro progress and the expected delivery dates.

2025Delivery milestones202620272028Hiring the Main PackagesMobilization and Civil WorksPower House ConstructionSubstations and Transmission LinesGenerating Unit InstallationCommercial OperationPerformanceOperating License ObtainmentBaseline (Plan)1st2nd3rd4thQuarter1st2nd3rd4thQuarter1st2ndQuarter3rd4thQuarter