Packaging SP Indaiatuba

Optimization

Installation of an automation system for intermediate stock, including:
  • Corrugator output
  • Intermediate inventory of sheets
  • Transfer cars for movement
  • Prefeeders on all printers

Impacts

  • Increased productivity of the printers
  • Reduction of scrap

Investment

The expansion of the Gaia IX project in progress has the following expectations:

Estimated investment

R$ 42.860 k

Planned execution time

28 months

Investment made (until 03/31/26)

R$ 37.764 k

Image Gallery

Follow the progress of the project

Delivery milestones

Progress

100%

Follow up the project stage macro progress and the expected delivery dates.

Delivery MilestonesIntermediate stock automationPrefeedersCivil adequacy2021202220242023Startup (Plan)Deadline (Plan)QuarterQuarterQuarter1st2nd3rd4th1st2nd3rd4th1st2nd3rdQuarter3rd4th