Paper SC Campina da Alegri

Expansion

  • A new wood yard
  • Recovery boiler Installation
  • New power cogeneration system
  • Interface improvement throughout this system
  • Evaporation and Non Condensable Gas (GNC) treatment expansion

Impacts

Production capacity

increase in brown Kraft pulp production
0 %
Power generation
increase of own power generation
0 %

Investment

Gaia I project ongoing expansion has the following expectations:

Estimated investment

R$ 682.023 K

Planned work execution term

30 months

Investment made (until 03/31/26)

R$ 658.621 k

Image Gallery

Follow the progress of the project

Gaia I diagram

Block diagram shows the areas to be affected and the equipment to be installed with the project.

Delivery milestones

Progress

100%

Follow up the project stage macro progress and the expected delivery dates.

2020Delivery milestones1st2nd3rd4th1st2nd3rd4th1st2nd3rd4th1st2nd3rd4th202120222023Basic Engineering (FEL 3)Infrastructure preparationRecovery BoilerCogenerationNew Wood YardNew ETA and ETACImprovements in the Firing, Washing and Caustification Areas Heat Recovery, GNC’S andEvaporation Recovery QuarterQuarterQuarterQuarterStartupDeadline (Plan)
2020TrimestreTrimestreTrimestreTrimestre202120222023StartupMarcos de entregaEngenhariaBásica (FEL 3)Preparação daInfraestruturaCaldeira de RecuperaçãoCogeraçãoNovo Pátio de MadeirasNova ETA e ETACMelhorias nas áreas de Cozimento, Lavagem e CaustificaçãoRecuperação de Calor, GNC'S eAmpliação da Evaporação