Gaia IX
Intermediate Inventory Automation

With the Gaia IX project, we will automate the output of the corrugator, the intermediate inventory of sheets, the installation of transfer cars and prefeeders, aiming to increase productivity and improve safety at work.

Modernization

  • 34 new dryer cylinders
  • Automation platform update
  • Rewinder safety

Impacts

  • Paper machine technology upgrade
  • 7% increase in paper production for corrugated cardboard packaging
  • Ensuring operational security

Investment

The current expansion of the Gaia XI project has the following expectations:

Estimated investment

R$ 89,668 K

Expected deadline for completion

33 months

Investment made (until 09/30/24)

R$ 68 K

Investment made (until 03/30/24)

R$ 6.308 K


Delivery milestones

Progress

98.1%

Follow-up the progress of project stages and expected deadlines in a macro level.

Delivery MilestonesDetailed EngineeringMP#5 Shutdown and StartupNegotiation of Packages and Pre-Shutdown PreparationsPerformance202420262025QuarterQuarterQuarter1st2nd3rd4th1st2nd3rd4th1st2nd3rd4thStartup (Plan)Deadline (Plan)