Paper SC Campina da Alegria

Modernization

  • Frequency conversion from 50hz to 60hz
  • New transmission line
  • New generators and turbines
  • Infrastructure improvements
  • New engine house

Impacts

Power generation
increase in powerplant average generation
0 %
increase in global average generation
0 %
The Gaia IV – Cristo Rei Repowering and Gaia V – São Luiz Repowering projects are currently under review due to the wait for the necessary environmental releases that imply budget and schedule adjustments for both projects. Meeting all legal and regulatory requirements and ensuring that the project is conducted in accordance with environmental sustainability standards is Irani’s commitment.

Impacts

Power generation
increase in powerplant average generation
0 %
increase in global average generation
0 %

Investment

The ongoing expansion, for the Gaia V project, has the following expectations:

Estimated investment

R$ 62,864 K

Planned work execution term

18 months

Image Gallery

Delivery milestones

Progress

60%

Follow up the project stage macro progress and the expected delivery dates.

20232024StartupDelivery milestonesEnvironmental LicensingIntegrated Environmental StudiesIrani River BasinEngineering and Physical worls1st sem1st sem2nd sem2nd semStartup (Plan)Term (Plan)

Ongoing activities

Documents

If you want more details about the Gaia V project, you can access them through reports and documents. Just download to access the material available.

– RELATÓRIO DE STATUS – GAIA V Acompanhe as etapas executadas até o momento, as etapas em andamento, os pontos de atenção e oportunidades.