Gaia III
MP#2 Reform

Technological update of paper machine at Paper Unit steps up the production process and generates direct business results.

Modernization

  • MP#2 with production increase due to higher speed and sheet width
  • New equipment and automations allow an increase in contribution margin

Impacts

Production capacity
increase in machine paper production
0 %

Impacts

Production capacity
increase in machine paper production
0 %

Products

Gaia III investments take place at the Paper Plant in Vargem Bonita (SC), and allow production increase of the following products:

Kraft tote bags for physical and on-line retail

Kraft paper bags for delivery and takeaway

Investment

The Gaia III project has the following indicators:

Estimated investment

R$ 66,844 K

Planned work execution term

18 months

Investment made (until 09/30/24)

R$ 59,806 K

Image Gallery


Delivery milestones

Progress

100%

Follow up the project stage macro progress and the expected delivery dates.

2020Delivery milestones202120222023Basic EngineeringElaboration of the FAIDescriptive reportsand negotiationsManufacturing and deliveryMP#2 shutdown for Retrofit | StartupPerformanceQuarterQuarterQuarterQuarter3rd1st2nd3rd4th1st2nd3rd4th1st2nd3rd4thStartup (Plan)Deadline (Plan)

Ongoing activities

Documents

If you want more details about the Gaia III project, you can access them through reports and documents. Just download to access the material available.

– RELATÓRIO DE STATUS – GAIA III Acompanhe as etapas executadas até o momento, as etapas em andamento, os pontos de atenção e oportunidades.