Paper SC Campina da Alegria

Modernization

  • 34 new dryer cylinders
  • Automation platform update
  • Rewinder safety

Impacts

  • Paper machine technology upgrade
  • 7% increase in paper production for corrugated cardboard packaging
  • Ensuring operational security

Investment

The current expansion of the Gaia XI project has the following expectations:

Estimated investment

R$ 89.668 k

Expected deadline for completion

33 months

Investment made (until 30/06/26)

R$ 78.732 k

Image Gallery

Follow the progress of the project

Delivery milestones

Progress

75%

Follow-up the progress of project stages and expected deadlines in a macro level.

Delivery MilestonesDetailed EngineeringMP#5 Shutdown and StartupNegotiation of Packages and Pre-Shutdown PreparationsPerformance202420262025QuarterQuarterQuarter1st2nd3rd4th1st2nd3rd4th1st2nd3rd4thStartup (Plan)Deadline (Plan)

Documentos

A expansão gerada pelo projeto Gaia II tem muitas fases e você pode acompanhá-las através dos relatórios, basta fazer download para verificar os detalhes de cada fase do projeto.

– RELATÓRIO DE STATUS – GAIA II Acompanhe as etapas executadas até o momento, as etapas em andamento, os pontos de atenção e oportunidades.