Packaging SP Indaiatuba

Otimization

Installation of an automation system for intermediate stock, including:

  • Corrugator output
  • Intermediate inventory of sheets
  • Transfer cars for movement
  • Prefeeders on all printers

Impacts

  • Increased productivity of the printers
  • Reduction of scrap

Investment

The expansion of the Gaia IX project in progress has the following expectations:

Estimated investment

R$ 42,860 K

Planned execution time

28 months

Investment made (until 09/30/24)

R$ 37,710 K

Image Gallery

Follow the progress of the project

Delivery milestones

Progress

100%

Follow up the project stage macro progress and the expected delivery dates.

Delivery MilestonesIntermediate stock automationPrefeedersCivil adequacy2021202220242023Startup (Plan)Deadline (Plan)QuarterQuarterQuarter1st2nd3rd4th1st2nd3rd4th1st2nd3rdQuarter3rd4th

Documentos

 A expansão gerada pelo projeto Gaia II tem muitas fases e você pode acompanhá-las através dos relatórios, basta fazer download para verificar os detalhes de cada fase do projeto.

– RELATÓRIO DE STATUS – GAIA II Acompanhe as etapas executadas até o momento, as etapas em andamento, os pontos de atenção e oportunidades.