Paper SC Campina da Alegria

Modernization

  • Installation of a primary equalization tank
  • New receiving tank for clarified effluent of the primary floaters
  • Two new aeration tanks
  • Building for installing air blower sets
  • Building for ECC (Engine Control Center)
  • Pressurized and automated disk filtration system
  • General overhaul of the current primary sludge drainage equipment
  • Installation of new process monitoring cameras for the new structures

Investment

The expansion of the Gaia VII project in progress has the following expectations:

Estimated investment

R$ 49,597 K

Planned execution period of

28 months

Investment made (until 09/30/24)

R$ 46,502 K

Image Gallery

ETP Phase 1 Expansion

Documentos

 A expansão gerada pelo projeto Gaia II tem muitas fases e você pode acompanhá-las através dos relatórios, basta fazer download para verificar os detalhes de cada fase do projeto.

– RELATÓRIO DE STATUS – GAIA II Acompanhe as etapas executadas até o momento, as etapas em andamento, os pontos de atenção e oportunidades.

Delivery milestones

Progress

100%

Follow up the project stage macro progress and the expected delivery dates.

Delivery MilestonesEnvironmental LicensesRerouting of the EffluentPipelineObtaining the Environmental Installation LicenseFiltering SystemEffluent Tanks StartupsEffluent Tanks ConstructionCompletion of the Construction202220212023QuarterQuarterQuarter1st2nd3rd4th1st2nd3rd4th4thStartup (Plan)Deadline (Plan)Startup (Tendency)